Wirral’s Borough Yard costs rise £21m as Sisk contract agreed
Wirral Council has agreed a £36.5m enabling works contract in principle, while changes to funding leave an £8.9m programme shortfall.
By Tom Ashworth, North West Correspondent ·

Wirral Council has agreed in principle to award John Sisk & Son a £36.5m contract to prepare Birkenhead’s 65-acre Borough Yard regeneration site for development, including 1,600 homes. The decision was taken on Wednesday following investigations and design work that have increased the cost of delivering the scheme.
The enabling programme has recorded a £20.7m increase against its earlier £57.1m budget, as reported by Place North West. Moving some infrastructure into a separate funding allocation reduces the remaining shortfall to £8.9m.
What happened
Sisk’s proposed contract covers remediation and engineering for the first two phases of Borough Yard. It also includes construction of the Mollington Link to Hind Street Active Travel Corridor and the Waterloo Place section of the Dock Branch South linear park.
Several substantial tasks sit outside the £36.5m package: relocating gas infrastructure, realigning the Kings Square link, drainage work with United Utilities and completing the rest of the linear park. Those excluded works are estimated to cost a further £31m.
The higher estimates follow site investigations, surveys and technical design development. Sisk carried out that preparatory work under a contract awarded by the council in 2025.
Borough Yard’s infrastructure decision follows other significant North West council commitments, including approval of the £130m Carrington Relief Road in Trafford.
The background
Previously known as Hind Street, Borough Yard is intended to turn former railway sidings and gasworks into a new neighbourhood. Alongside the housing, the approved plans provide for a park and 650,000 sq ft of commercial space.
Planning approval was granted in October last year. Wirral Council is developing the scheme with ION Developments and Picture This, bringing together the local authority and private-sector partners for the redevelopment.
The project has secured £52.1m from Liverpool City Region Combined Authority and Homes England. That funding supports a scheme requiring substantial work to make former industrial land ready for construction.
Elsewhere in the region, Warrington is seeking views on a plan for 13,250 homes. Borough Yard is further through the planning process, with the current decisions focused on preparing its approved development site.
The detail
Wirral Council has identified a separate route to fund the Kings Square link and linear park works. Both will draw on the borough’s £29m allocation from the combined authority’s Transport for the Regions funding.
Once those elements are removed from the enabling package, the programme is expected to cost £66m. That leaves £8.9m to be covered against the original £57.1m budget; the transport funding change therefore reduces, rather than eliminates, the gap.
The use of a separate transport allocation comes as councils across the region commit infrastructure funding, including Lancashire’s £643m transport plan with rail funding.
At the same meeting, councillors agreed to enter a £2.9m development management agreement with ION. Under that arrangement, the developer will oversee the enabling works for the council. Drees & Sommer is the authority’s NEC consultant on Borough Yard.
What happens next
The next step is the award of Sisk’s enabling works contract following the council’s agreement in principle. Its scope is confined to the specified remediation, engineering, active travel and park works, rather than construction of the planned homes or commercial buildings.
The reported decisions do not identify how the remaining £8.9m shortfall will be funded or give a completion date for the enabling programme.
Why this matters
For businesses considering future premises in Birkenhead, Borough Yard offers a planned 650,000 sq ft of commercial space alongside 1,600 homes. The enabling works agreement advances preparation of the former industrial site, but an £8.9m shortfall remains after some infrastructure shifts to transport funding. Developers, contractors and prospective occupiers therefore have greater clarity on the next package of work, but no reported completion date on which to base investment or relocation plans.
Frequently asked questions
- What is Borough Yard in Birkenhead?
- Borough Yard is a 65-acre redevelopment of former railway sidings and gasworks in Birkenhead. Previously called Hind Street, it has approval for 1,600 homes, a park and 650,000 sq ft of commercial space.
- Why have Borough Yard’s costs increased?
- Site investigations, surveys and technical design development have led to higher enabling works estimates. The reported increase is £20.7m against the previous £57.1m budget, before some infrastructure is moved into separate transport funding.
- What will Sisk build at Borough Yard?
- The proposed £36.5m contract covers remediation and engineering for the first two phases, the Mollington Link to Hind Street Active Travel Corridor and the Waterloo Place section of Dock Branch South linear park.
- How much is Borough Yard’s funding shortfall?
- After the Kings Square link and linear park elements move into a separate transport allocation, the enabling programme is expected to cost £66m. That leaves an £8.9m shortfall against the earlier £57.1m budget.
- Who is developing Borough Yard?
- Wirral Council is developing Borough Yard with ION Developments and Picture This. The council has also agreed a £2.9m arrangement for ION to manage the enabling works on its behalf.
- Who is funding Borough Yard?
- Borough Yard has received £52.1m from Liverpool City Region Combined Authority and Homes England. Kings Square link and linear park works will use part of Wirral’s £29m Transport for the Regions allocation.
- When will Borough Yard be completed?
- The reported council decisions do not provide a completion date. The next stage is the award of Sisk’s enabling works contract, which has been agreed in principle.
In this story
Topics: Wirral Borough Yard · Borough Yard Birkenhead · Borough Yard costs · Sisk Borough Yard contract · Hind Street regeneration · Wirral Council housing development · Birkenhead regeneration · All Regional Business – North West news →
Original reporting: Place North West. This article is an independent write-up by British Business Echo.
Latest from the newsdesk
- E-commerce
Meta launches Muse shopping agent with major UK retailers
- Funding & Business Finance
British Business Bank takes £43m Oxford Science Enterprises stake
- Business Mistakes / Lessons Learned
Next business data accessed in supplier cyberattack
- Business Growth
UK pork producers secure Vietnam access and Philippines deal
- Business Regulation
HSE tools help small firms check health and safety duties
Related stories

Lancashire approves £643m transport plan with rail funding
The four-year programme includes £28.2m for Cottam Parkway, station upgrades and bus investment, with major rail reopenings left for further development.

JLR adds hybrid option to electric Defender Sport plans
The smaller Defender will use JLR’s EMA platform as the group broadens powertrain choice and prepares to expand the brand beyond its current range.

SCALE Manchester names four founders for £13,000 support pitch
Four health and workplace businesses will pitch at Freight Island on 25 November for a support package worth almost £13,000.

Trafford approves £130m Carrington Relief Road by one vote
Trafford councillors back the 2.7-mile road by seven votes to six, with construction expected to start in 2030.